Customer Projects
| Project |
New Abattoir Extension and Panel Replacement Project for Cranswick
Foods PLC, Preston, Hull |
|
| Contract Value |
Total value £865,000 |
| Details |
Cranswick Foods Preston: New abattoir extension. Installation
of Mineral Wool and PIR cored panels to form walls and ceilings,
along with associated doors.
Panels were installed to provide production areas, rapid chill
facility, fire compartment walls between production and amenity,
chilled holding areas and loading dock. Whilst the project
was being carried out further extensive works were being undertaken
to remove and replace existing polystyrene cored panels to
the sites main butchery plant. PIR cored panels were used
as part of Cranswick Foods programme to upgrade their facilities
in relation to fire risk management. This particular project
required careful project management as the butchery had to
remain in production throughout.
|
|
| Project |
New Bacon Processing Facility for Cranswick Gourmet Bacon,
Sherburn In Elmet |
|
| Contract Value |
£750,000 |
| Details |
In 2006 GPL Construction were awarded the contract to supply
and install the insulated wall and ceiling panels along with
specialist doors to form a new bacon processing facility.
In 2010 GPL returned to site to commence works on phase 2,
involving the expansion of the unit with a new slicing hall,
chills, blast and holding freezers, dry goods store and amenity
block.
Walls and ceilings were formed using a combination of panel
types subject to location and application. With Mineral Wool
being used to form 1 and 2 hour fire walls and ceilings to
the dry goods stores and amenity areas and PIR cored panels
to form the main production area walls and “walk-on”
ceilings.
GPL were also responsible for the supply and installation
of the internal and external doors ranging from fire rated
and non-fire rated personnel doors, insulated hinged and sliding
doors, rapid roll doors, sectional doors and fire shutters.
The first part of the project was completed in December 2010
ready for the client to meet the needs of its Christmas orders.
Post-Christmas saw extensive alterations to the original facility
to provide a fully integrated unit.
Management of the overall contract has been achieved through
the setting up of a project team headed up by Cranswick Foods.
|
|
| Project |
Extension to High care Production area Tilmanstone Salads |
|
| Contract Value |
£132,000 |
| Details |
This 360 square metre extension to the high care production
area at Tilmastone Salads was carried out using Mineral Wool
core installation panels from Eurobond Laminates with external
grade panels to form the outside shell. Close involvement
was required with the client to allow smooth and safe running
of the existing production facility, whilst internal work
was carried out. |
|
| Project |
Berry Gardens New CA Stores |
|
| Contract Value |
£190,000 |
| Details |
This project incorporated the construction of new CA stores
for blueberries with an extension to the packaging area and
label and printing room. The project was particularly challenging
in that the structural floor of the existing building had
to be broken out and removed to a depth of 2 metres and re-instated.
A number of blueberry stores were constructed each designed
to allow Berry Gardens to import blueberries in container
loads and hold under controlled atmosphere conditions. The
outcome has extended shelf life whilst maintaining a high
quality product. |
|
| Project |
Pinguin Lutosa UK Refurbishment to existing factory |
|
| Contract Value |
£290,000 |
| Details |
GPLs undertaking was to refurbish the existing food production
area. The project included, removal of old, damaged polystyrene
panels, lining the existing external walls with new PIR, hygienic,
food safe panels and installing a new hygienic PIR ‘walk
on’ panelled ceiling. The project included cladding
around columns and existing services. Existing personnel doors
were replaced with new hygienic doors and in some instance
1hr fire rated doors. This was a relatively complex job with
tight time scales, our panel works, were integrated with new
machinery installation, floor repairs and service installations.
Throughout the project we worked successfully co-ordinating
with the client, the equipment suppliers and the electrical
and mechanical contractors. |
|
|